Great Central Railway has launched a tender process for a £3.5m construction phase that will add 60 metres of new railway to its long-running Reunification project.

The Factory Flyover scheme will involve an elevated concrete viaduct over a factory car park and a new bridge across Railway Terrace Road in Loughborough. A contractor is expected to be appointed before Christmas, with work due to start in early 2027 and finish before the end of the year.

The latest phase is part of the heritage railway’s plan to reconnect its surviving Leicestershire and Nottinghamshire sections, restoring 500 metres of track removed in the 1970s.

Malcolm Holmes, GCR general manager said: “This is a hugely significant moment for us.  We’re actually building two sections of the Reunification project at the same time. The new bridge and viaduct will add to the three pieces of Reunification already built, taking our total investment in the project so far to £8.5m, the vast majority being contributed by supporters around the world. It’s their passion which has helped us get this far.”

Three major elements of the reunification scheme have already been delivered, including a new bridge over the Midland Main Line at Loughborough, restoration of a historic canal bridge and replacement of a road bridge.

The completed link is intended to create an 18-mile heritage railway between the two counties, with vintage bus services providing additional visitor connections.

GCR expects the reunited railway to attract hundreds of thousands of visitors to the East Midlands, support around 150 jobs and contribute an estimated £250m to the regional economy over 30 years.

Andy Fillingham of the Great Central Railway (Nottingham) said, “Earlier this year we hosted Flying Scotsman and Tornado together and we could see the appetite everyone has for completing the link and running trains along 18 miles. This project was once described as impossible and while there is much more to do, these next two stages, being built at the same time, will prove we are as committed as ever to finishing it!”

Further investment of around £18m will be needed after the Factory Flyover work to complete the railway, rebuild locomotive sheds and prepare for the final connection between the two sections.