Hospital chiefs consider legal action over stalled Liverpool scheme

Plans for The Royal Liverpool Hospital

Hospital bosses are considering legal action after further delays to Liverpool’s new £335m Royal Hospital.

The Royal Liverpool and Broadgreen University Hospitals NHS Trust has confirmed that the hospital will now not open until 2022.

It was originally scheduled to open early in 2017.

Also, costs for repair and remediation work at the troubled site have almost doubled to nearly £600m.

Work stopped in January 2018 when construction giant Carillion went bust with debts of £1.5bn.

The developer began construction, next to the current Royal Hospital, in February 2014, but just over two years later Carillion confirmed the job was running six months behind schedule.

Work was temporarily halted in December 2016 when a cracked beam was discovered. Further delays followed in March 2017 when Carillion put back the opening to Summer 2018.

In June 2017 concerns were raised over the building’s cladding, following the Grenfell Tower tragedy. Then, in December, shortly before Carillion’s collapse, the opening date was moved back indefinitely.

Further structural problems were discovered, but in November 2018 builder Laing O’Rourke was appointed to rectify the various issues at the site.

In June this year Liverpool Mayor Joe Anderson called for a public inquiry into the scheme after further defects were found.

And this week, hospital chief executive Steve Warburton said work will not be complete until 2022, and the costs are now expected to be £300m. This is on top of the £285m already spent on the building.

Mr Warburton said: “In simple terms, there are a whole series of structural failures and then cladding failures as well.

“It will take a huge amount of work to replace that cladding.”

Following news of the latest delay staff have removed some equipment already installed in the new hospital, to the old Royal so staff there can use it.

Mr Warburton said the trust is still finalising its business case for the extra work, which is expected to be ready in February.

Previously, the Government said it would stand the extra costs, and Mr Warburton said he expects that to still be the case.

Now, the trust is considering whether to take legal action over the catastrophic programme.

A spokesperson told TheBusinessDesk.com: “We are looking at whether we can take legal action, in conjunction with NHS England.”

However, they said they cannot identify who could face legal proceedings “so as not to prejudice any future action”.

Unite the Union regional officer Derek Jones said: “The public and the Royal’s workforce have been completely let down by the Government’s abject failure to get to grips with the Carillion disaster and its aftermath.

“The Government appointed Carillion to build the hospital, neglected to monitor the project’s progress and failed to ensure there was no delay in getting it built once the firm went under.

“Because of this, staff and patients will now have to spend three more Winters in a building that is not fit for purpose.

“The Royal is completely unsuited to meeting the needs of patients, who only continue to receive excellent care because the hospital’s exemplary staff manage to find ways to work around the crumbling infrastructure.”

Click here to sign up to receive our new South West business news...
Close