Water main delays push long-awaited bypass opening back to winter 2027
The opening of the Banwell bypass has been delayed by six months to winter 2027 because of hold-ups to water main diversions.
The water main works, managed by Bristol Water, involve relocating underground services from the construction area so that water supplies to local properties can be maintained and accessed in future.
The bypass construction requires ground improvements including piling, which cannot begin until the water main diversions are completed.