Winvic Construction has been awarded the eighth contract to build a net zero carbon industrial warehouse at the 700-acre SEGRO Logistics Park East Midlands Gateway (SLPEMG).

It is the first speculative development at the park, which is adjacent to East Midlands Airport and 1.5 miles from the A42/M42 connection at J23A, and the £9m project will be completed in November 2021.

The 200,000 sq ft unit will be cold store ready and have 17 docks, four Euro docks and four level access doors.

The scheme comprises 10,000 sq ft of two-storey office accommodation, a 3,000 sq ft transport office, a 55m yard, and parking for 170 cars and 45 HGVs.

Winvic has had a presence on the SLPEMG site since its inception February 2017 when the main contractor began the civils and infrastructure work to facilitate the park and a Strategic Rail Freight Interchange (SRFI) and is currently constructing two other industrial warehouses.

One of which is a 694,000 sq ft facility for DHL, which comprises two mezzanine levels and over 25,000 sq ft of two-storey integral offices. The second facility is a 150,000 sq ft fulfilment centre with ancillary offices, car parking including double-deck parking for 200 electric vans and lorry loading facilities.

Danny Nelson, Winvic’s head of industrial, distribution and logistics, said: “We’re thrilled that the SEGRO team has once again put its trust in Winvic at SLPEMG, and this eighth unit means we have three separate project teams working at the 700-acre site.

“The short 26-week programme means we will be handing the scheme over in November of this year, and we are ready to assist with fit out when a tenant is secured.”

Andrew Pilsworth, managing director, national logistics at SEGRO, said: “This speculative development is really exciting, as it highlights our confidence in the ongoing demand for well located, connected, modern space in the East Midlands and underpins the importance of logistics. Including this speculative build, Winvic is currently constructing three units for us at this site and the company’s expertise with net zero carbon projects is evident. With the park nearly 75% full, we’ll be working hard over the coming months to secure customers for the spec build and the remaining 1.5m sq ft of space to ensure that SEGRO Logistics Park East Midlands Gateway can continue to play a key role in creating jobs and economic growth in the region.”